Find programs in your area

Enter your postal code:

Available Incentives

Attractive and Easy to Earn.  Each of the four Commissioning Phases offers an incentive.

Scoping Study Phase incentive

The lesser of:
  • The amount actually owing and paid to the Commissioning Agent for preparing the Scoping Study Report, excluding applicable taxes, or
  • $2,500

In each case, less any other financial incentives provided by the province of Ontario.


Investigation Phase Incentive Calculated at:

  • $18 per ton of Chilled Water System cooling, up to a maximum of 75% of the amount actually owing and paid to the Commissioning Agent for preparing the Investigation Phase Commissioning Report, excluding applicable taxes, plus
  • $6 per ton of Chilled Water System cooling, up to a maximum of 75% of the eligible costs of acquiring and installing the Data Acquisition System

Up to a maximum of $30,000, less any other financial incentives provided by the province of Ontario.


Implementation Phase Incentive

The lesser of: 
  • The amount actually owing and paid to the Commissioning Agent for preparing the Implementation Phase Commissioning Report, excluding applicable taxes, and
  • $5,000

In each case, less any other financial incentives provided by the province of Ontario.

Plus only for measures with a project pay back of more than two years, the lesser of:

  • The greater of Implementation Phase Energy Savings x $0.10/kWh and Implementation Phase Demand Savings x $800/kW, less any other financial incentives provided by the province of Ontario
  • 50% of the eligible costs of purchasing and installing the major measures, excluding applicable taxes, and the total of any other financial incentives provided by the province of Ontario

Hand-Off/Completion Phase Incentive

The lesser of: 
  • The amount actually owing and paid to the Commissioning Agent for preparing the Hand-off/Completion Phase Commissioning Report, excluding applicable taxes, and
  • $2,500 less any other financial incentives provided by the province of Ontario.

In each case, less any other financial incentives provided by the province of Ontario


Get Started - Contact your Local hydro company

© 2017 Independent Electricity System Operator. All rights reserved. OM Official Mark adopted and used by the Independent Electricity System Operator
jQuery UI Accordion - No auto height